Panama Canal

The consortium building the third set of locks for the Panama Canal is making fresh claims for cost overruns totaling $737 million, officials said Friday.
Canal administrator Jorge Quijano told reporters that the Panama Canal Authority had received two claims on Tuesday that "will be evaluated" to determine if there is probable cause.
But he warned that "at first glance, the issues will be very difficult for the counterparty to justify."
One of the claims, for $333 million, is related to the weight of the gate for the locks -- at 55,000 tonnes, compared to the 35,000 tonnes initially planned.
But Quijano pointed to a clause in the contract, according to which the canal authority would pay up to the value of a gate weighing 49,000 tonnes.
The second claim, for $404 million, is due to delays in the fourth phase of excavation in the Pacific sector.
The consortium, Grupos Unidos por el Canal, says that the delay in excavation work may mean it will not receive water needed to test the gates.
Quijano, however, said he has a "plan B" to provide the necessary water for testing.
The canal authority will pay another $120 million in adjustments to the contract and other small claims, Quijano said.
Work began in 2007 to expand the canal with a third set of locks to enable it to handle the modern mega-freighters that global shipping companies prefer.
But the $5.25 billion project has been plagued by delays, strikes and a bitter dispute over $1.6 billion in cost overruns with the consortium carrying out the upgrade, led by Spanish construction firm Sacyr.
Initially scheduled for completion in 2014, the project's due date has been pushed back to early 2016.
Nearby Nicaragua, meanwhile, launched construction this week on a rival canal, a $50 billion project that the Chinese firm behind it plans to complete in five years.