DEWA inaugurates 400/132kV substation

Arab Today, arab today

Arab Today, arab today DEWA inaugurates 400/132kV substation

DEWA inaugurates 400/132kV substation
Dubai - WAM

Saeed Mohammed Al Tayer, MD and CEO of Dubai Electricity and Water Authority, DEWA, inaugurated the 400/132 kilovolt (kV) substation at the Mohammed bin Rashid Al Maktoum Solar Park.

The AED275 million substation is one of the first projects of the solar park and has a conversion capacity of 1,515 megavolt amperes, MVA. It will transmit and transform electricity produced from solar energy and connect it to DEWA’s grid. The substation is the first of its kind in the UAE to integrate clean energy with traditional energy grid.

The inauguration was attended by senior officials from the Swiss firm ABB, the main contractors of the project, and senior officials from DEWA. Frank Duggan, President of Asia, Middle East and Africa (AMEA) at ABB, also attended the event.

Al Tayer, accompanied by ABB officials, also toured the project site that has four sections. The first includes a 400kV substation with 11 gas-insulated switchgears, GIS,. The second section converts from 400 kV to 132kV with a conversion capacity of 1,515 MVA. It includes three 400/132 kV interconnecting transformers. The third section has 21 GIS while the fourth section houses the control and safety facilities. ABB co-operated with a number of companies, including Energo and Comodor, to complete the project.

"I am pleased to welcome you all to the inauguration of the 400/132 kV substation at the Mohammed bin Rashid Al Maktoum Solar Park, which was constructed in adherence to the vision of the Vice President and Prime Minister and Ruler of Dubai, His Highness Sheikh Mohammed bin Rashid Al Maktoum, which is a roadmap we follow in all our work, initiatives, and development projects. This project supports the Dubai Plan 2021 to transform Dubai into the preferred place to live, work and visit. The 400/132kV substation, with an investment of AED275 million and a conversion capacity of 1,515 megavolt amperes (MVA), is one of the first projects of the Mohammed bin Rashid Al Maktoum Solar Park, and will connect and transmit the energy produced from solar power generation to DEWA’s grid. It is the first substation of its kind in the UAE, which integrates clean energy with the traditional energy network," Al Tayer said.

He said that DEWA is now working on increasing the transmission capacity of the substation and its efficiency through three 400kV GIS bays, one 400/132kV Inter-connected transformer ,ICT, with a capacity of 505 MVA, nine 132kV GIS bays and four 132kV shunt reactors.

"ABB is pleased to support Dubai’s clean energy vision by being a technology partner to DEWA at the Mohammed bin Rashid Al Maktoum Solar Park. As a leader in the energy revolution, ABB is perfectly positioned to support growth of renewables in the UAE energy mix and strengthen its power infrastructure," Duggan of ABB said.

arabstoday
arabstoday

Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

dewa inaugurates 400132kv substation dewa inaugurates 400132kv substation

 



Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

dewa inaugurates 400132kv substation dewa inaugurates 400132kv substation

 



GMT 12:47 2017 Sunday ,05 November

HRH Princess Sabeeka to patronise key conference

GMT 14:40 2013 Saturday ,08 June

Modern twist on traditional kaftans

GMT 06:43 2016 Monday ,26 December

China To Pilot Supervisory System Reform

GMT 20:28 2017 Tuesday ,19 September

Clarins unveils 12 Day Christmas Calendar

GMT 18:47 2017 Sunday ,22 October

El-Sissi vows to quash terrorism

GMT 06:15 2017 Friday ,24 November

Hazza bin Zayed opens ninth edition of Abu Dhabi Art

GMT 10:22 2016 Wednesday ,23 March

cartoon twelve

GMT 23:22 2017 Friday ,24 November

3rd Annual UAE eHealth Week to start Sunday

GMT 21:15 2018 Wednesday ,31 October

Saudi Arabia reduces budget deficit by 60%

GMT 13:57 2011 Monday ,24 October

Germany to vote Wednesday on rescue fund boost

GMT 05:50 2018 Friday ,12 January

'Global shift' as Olympics set up shop

GMT 07:48 2010 Wednesday ,15 September

Debt deal likely to lift markets
Arab Today, arab today
 
 Arab Today Facebook,arab today facebook  Arab Today Twitter,arab today twitter Arab Today Rss,arab today rss  Arab Today Youtube,arab today youtube  Arab Today Youtube,arab today youtube

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©

arabstoday arabstoday arabstoday arabstoday
arabstoday arabstoday arabstoday
arabstoday
بناية النخيل - رأس النبع _ خلف السفارة الفرنسية _بيروت - لبنان
arabstoday, Arabstoday, Arabstoday