Up to 157.260 million cubic meters of water-saturated sand have been dredged so far as part of the Suez Canal Development Project, said executive director supervising the dredging process Wagdi Zaki.
This represents 62.9 percent of a total 250 million cubic meters that should be dredged as part of the project, he added in statements Thursday.
As many as 37 dredgers are working in the project, he noted.
The project aims at expanding the Suez Canal region's role as a global, industrial, and logistics center that is environmentally balanced with an integrated economy.
It is also projected to become a global hub due to its logistics and industrial services.
The project was funded through granting investment certificates to Egyptians with 12% returns, and in eight days, more than 60 billion pounds were collected.
GMT 14:03 2018 Thursday ,13 December
Ports of Lattakia, Tartous re-opened for maritime navigationGMT 13:35 2018 Tuesday ,11 December
Harbors in Lattakia and Tartous closed due to weather conditionsGMT 18:43 2018 Wednesday ,31 October
Egyptian pollution plan signals the last straw cloudGMT 12:04 2018 Friday ,26 October
At least 18 school children die in Jordan flash floodGMT 14:39 2018 Tuesday ,23 October
Cabinet denies Greater Cairo to be hit by floods in coming daysGMT 04:11 2018 Tuesday ,25 September
Necessary preparations to face possible winter floodsGMT 15:05 2018 Saturday ,22 September
Farm burns during Israeli army raid of West Bank villageGMT 16:58 2018 Tuesday ,18 September
"Bakri" Early Preparation for Winter Agricultural SeasonMaintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©
Send your comments
Your comment as a visitor